US energy sec floats faster grid access for AI and crypto miners
Summary
US Energy Secretary Chris Wright sent a letter to the Federal Energy Regulatory Commission (FERC) requesting new rules to expedite the process for large electricity consumers, such as AI data centers and Bitcoin mining operations, to connect directly to the high-voltage transmission system. Wright noted that US electricity demand is growing rapidly due to these large loads. The proposed rules would mandate expedited reviews, potentially completing them in 60 days instead of years, provided applicants agree to cover necessary network upgrades. S. Matthew Schultz, CEO of CleanSpark, praised the move, viewing it as recognition of flexible demand's value in strengthening the grid. Wright has asked FERC to respond to the letter by April 30, 2026.